PULASKI COUNTY (9-10) – Continued work on Interstate 30 in Little Rock and North Little Rock will involve lane closures, according to Arkansas Department of Transportation (ARDOT) officials.

Weather permitting; the following travel impacts and traffic pattern changes will occur the week of September 13, including detour routes.

North Little Rock

Mon., Sept. 13 – Tues., Sept. 14

  • 10 p.m. – 5 a.m. | I-40/I-30 Interchange | Overnight single and double-lane closures. Lane closures include I-40 eastbound and I-30 eastbound lanes through the north terminal to the North Hills Blvd. off ramp (Exit 154). Double-lane closures will be limited from 11 p.m. to 5 a.m.

Mon., Sept. 13 – Sat., Sept. 18

  • 8 p.m. – 5 a.m. | I-40/I-30 Interchange | Overnight traffic shift and lane closures at the north terminal. I-40 eastbound traffic will shift to the north. Lane closures include I-40 eastbound and westbound through the interchange.

Little Rock

Mon., Sept. 13

  • 8 p.m. – 5 a.m. | 2nd St. westbound | Overnight left-lane closure between Rivermarket Ave. and Cumberland St. Watch for flagging operations.

Mon., Sept. 13 – Sat., Sept. 18

  • 9 a.m. – 3 p.m. | I-30 Frontage Road northbound | Daytime single-lane closure between 6th and 3rd Sts. Single-lane closures include one block of 4th St. east to Collins St. and one block of Collins St. north to 3rd St.
  • 9 a.m. – 3 p.m. | I-30 Frontage Road | Daytime single-lane closures between 10th and
    6th Sts.
  • 9 a.m. – 3 p.m. | 4th St. intersections with Rock St. and River Market Ave. | Daytime right-lane and sidewalk closures at the intersections. Pedestrian detours will be signed for sidewalk closures. Some street parking will be impacted. Watch for flagging operations.
  • 8 p.m. – 5 a.m.  | I-30 between the Arkansas River and I-630 | Overnight single and double-lane closures. Double-lane closures will be limited from 11 p.m. to 4 a.m.
  • 10 p.m. – 5 a.m. | I-630 eastbound ramp to I-30 eastbound | Overnight ramp closure. Detour will use the I-630 eastbound ramp to the I-30 frontage road and travel northbound to the interstate on-ramp at 6th St.
  • 8 p.m. – 5 a.m. | I-30 westbound to I-630 ramp (Exit 139B) | Overnight lane shift and single-lane closure on the exit ramp.

Traffic will be controlled by construction barrels and signage. Drivers should exercise caution when approaching and traveling through all highway work zones. Additional travel information can be found at IDriveArkansas.com or ARDOT.gov. You can also follow us on Twitter @IDriveArkansas for traffic and @myARDOT for everything else.